Specialized foundation engineering for complex ground conditions and high-load structures, including assessment, design recommendations and construction support
Civil structures design and supervision with practical oversight from concept through execution
Technical due diligence and feasibility studies for civil and construction projects, including site reviews, option analysis, risk evaluation and implementation advice
Quality assurance, occupational health and safety compliance, and environmental management planning to support safe and sustainable project delivery
Managed contract administration, supporting claims, variations, certificates, and dispute avoidance to ensure project compliance and satisfaction
Prepared Bills of Quantities, tender documentation, and cost estimates to guide procurement strategies and optimise budgeting during competitive bidding
Engaged stakeholders, advised clients, and produced structured project reports to align decision-makers and enhance communication throughout project delivery
Provided consultancy services to clients in civil engineering, focusing on project planning and execution.
Mentoring and technical oversight of junior engineers, inspectors and site teams to strengthen delivery standards and professional development
EMPLOYER'S REPRESENTATIVE / RESIDENT ENGINEER
RAUBEX-ZIMBORDERS JV
Beitbridge
2021.01 - 2024.12
Oversaw projects valued at USD 300 Million, ensuring successful execution and delivery
Managed project budgets, ensuring financial compliance, accurate interim payment certificates, and adherence to quality and OHS standards
Supervised 600+ labourers, 100+ artisans, and 14+ engineers to deliver project objectives
Construction and supervision of Beitbridge Border Post Modernisation Project
Harare-Beitbridge Highway Dualization
Freight Terminal, Bus Terminal, Vehicle & Pedestrian Terminal construction
ZIMRA Village Cluster Housing & Flats; sewer and water reticulations
PROJECT MANAGER
BCC-UNIK CONSTRUCTION ENGINEERING / ICE JV
2019.10 - 2020.12
Managed team of 150+ labourers, 40+ artisans, and 4 engineers, ensuring project adherence to timelines and quality standards
Evaluated project budget of USD 200 million
Calibrated hydraulic models and established discrete pressure zones, enabling effective NRW analysis
Conducted hydraulic modelling of sewerage network, identifying problematic areas for BCC
Upgrading, renewal and replacement of water mains; supply of domestic water meters
Assessed surface water sources (Mthabezi, Mzingwane, Upper Ncema, Inyankuni, Insiza)
Bulawayo Water and Sewerage Service Improvement Project (BWSSIP)
Managed Kafue-Lusaka bulk water transmission pipeline project (120 km) to improve water supply reliability in the region.
Coordinated extension and refurbishment of University Training Hospital (UTH) 200-bed block (USD 400M) to enhance healthcare capacity.
Supervised 400 labourers, 100 artisans, and 12 engineers on site to ensure project adherence to timelines and quality standards.
Millennium Challenge Account Zambia Projects — Lusaka drainage, water reticulation and sewerage
Smart Safe Water Scheme Scaling Up Project, Jack Compound, Lusaka
Non-Revenue Water Surveys; WASH projects in Lusaka townships
Value: USD 800 Million
CONTRACTS MANAGER / PROJECT MANAGER
NEWBASE CIVIL & N-FRASYS INFRASTRUCTURES JV
2015.09 - 2016.08
Managed OHS plans and EMP submissions while ensuring compliance with FIDIC, GCC, and NEC contract management standards
Oversaw construction of Mapai Hospital, Dr. Fernando Nobre General Hospital & Training Institute, delivering a 25-bed, two-floor building
Constructed mass residential housing for Mimosa Mining, including single and double-storey apartments and facilitated water and sewer reticulations
Constructed high voltage pylon and substation in Mapai/Gaza, Mozambique.
Performed maintenance works on mine tailing dams in Zvishavane, Zimbabwe.
Value: USD 10M — USD 25M
CONTRACTS MANAGER
IMBUMB A ASPHALTING & EARTHWORKS CIVIL & CONSTRUCTION ENGINEERS
Durban
2014.01 - 2015.09
Managed GCC, NEC, and JBCC contracts, ensuring compliance and timely execution across projects.
Value: ZAR 500M + ZAR 40M
Constructed 6 megalitre concrete tank for water reservoirs in Zululand, enhancing local water supply.
Executed 3,000m bulk water pipeline construction in Zululand, improving infrastructure reliability.
R. Khan Hospital — additional 20-bed hostel (ZAR 40M); Uphongolo General Hospital extension (ZAR 15M)
Road construction for KwaDukuzwa Township KZN — 100 km
Road maintenance and surfacing — Durban Metropolitan 200 km (eThekwini Municipality)
CONTRACTS MANAGER / RESIDENT ENGINEER
MADZ BUILDING & CIVIL ENGINEERING CONTRACTORS
Harare
2010.01 - 2013.12
Assessed project value of USD 20 million for budgeting and financial planning
Led mass housing construction for 150 units dedicated to mining employees — 150 units for mining employees
Developed turf water reservoirs at Zimplats for efficient water storage — Zimplats/Ngezi Mining Compound; 5 megalitres ground and elevated tanks
Installed bulk water pipeline using 8,000m of UPVC, steel, and concrete pipes — 8,000m UPVC/Steel/Concrete pipes
Managed tailings at Ngezi Mine, implementing new sewer reticulations for Turf Mining Location
Constructed main sewer line and commissioned tailing and sewer ponds
Constructed new mining hospital featuring emergency wards and outpatient facilities — emergency wards and outpatient facilities
PROJECT ENGINEER
SYNOHYDRO CIVIL ENGINEERING & CONSTRUCTION
2006.01 - 2009.12
Supervised structural steel installation, earthworks, and concrete projects, ensuring compliance with FIDIC/GCC/NEC/JBCC contracts and industry standards.
Dualization of Francistown to Ramokwebana Road — 160 km (BW 800M)
Game City Mall — 120+ commercial shops (BW 1 Billion)
Gaborone Private Hospital — medical and surgical wards, 200+ beds (BW 400M)
Extension and renovation of Bokamoso Private Hospital — 160+ beds (BW 200M)
Upgrading of Sir Seretse Khama International Airport — water and sewer reticulations (BW 600M)
Value: BW 200M — BW 1 Billion per project
SITE AGENT
COSTAIN CIVIL ENGINEERING & CONSTRUCTION (PTY) LTD
2003.01 - 2005.12
Oversaw daily operations of 500 labourers, 100 artisans, and 12 engineers on construction sites, ensuring project timelines and quality standards were met.
Completed multi-story building for Reserve Bank of Zimbabwe, enhancing financial institution's operational capacity.
Construction of BTV Complex in Gaborone — 4 stories (BW 150M)
Constructed students' dormitories for Ministry of Higher Education at Domboshawa Training Centre, supporting educational infrastructure development.
Construction of Domboshawa Sewer Ponds; Rural Medical Centre — 50 beds
Upgrading, rehabilitation and paving of roads in various urban and rural districts
CIVIL ENGINEER / SITE AGENT
MINISTRY OF PUBLIC CONSTRUCTION & NATIONAL HOUSING (MPCGNH)
1999.01 - 2002.12
Managed over 10,000 labourers, 400 artisans, and 200 engineers to ensure project delivery
Oversaw project budget of ZWD 10 billion to ensure financial compliance and resource allocation
Chitungwiza General Hospital and Specialized Intensive Unit Construction
Harare General Hospital — Maternity Wing, Theatre, Paediatric Wards, Radiology, Renal Unit — 500+ beds
Renovated and upgraded District Hospitals across 10 provinces to enhance healthcare facilities
Multi-Story Government Composite Offices in all 10 provinces
Low, medium and high-rise residential units and services across 10 provinces
Non-Revenue Water Surveys; WASH projects; sewer and water reticulations
Students Hostels at University of Zimbabwe
Education
CERTIFICATE - URBAN WATER DEVELOPMENT CPD TRAINING AWARD
Engineering Institution of Zambia (EIZ)
2017-01
CERTIFICATE - LEVEL 2 AWARD IN SUPERVISING STAFF SAFELY
British Safety Council — MCAZ
Lusaka, Zambia
2017-01
DIPLOMA - ENVIRONMENTAL HEALTH AND SAFETY MANAGEMENT
Zimbabwe Institute of Management
2012-01
CERTIFICATE - COMPUTERIZED ACCOUNTING (ACC-PAC FOR WINDOWS)
Gaborone Technical College
Botswana
2003-01
CERTIFICATE - CIVIL & CONSTRUCTION ASSESSOR & VERIFIER
Botswana Ministry of Education — Dept. of Vocational Education
2001-01
DEGREE - BSC CIVIL ENGINEERING (HONOURS)
University of Zimbabwe (UZ)
Harare, Zimbabwe
1998-01
ADVANCED LEVEL (A LEVEL) FORM 6 - Mathematics, Physics, CDhemistry, Geography
Civil Engineering Designer/Senior Construction Inspector at R.M. Towill CorporationCivil Engineering Designer/Senior Construction Inspector at R.M. Towill Corporation